孫淑萍 王銘明
摘要:本文對杭州市某標(biāo)準(zhǔn)廠房及科研開發(fā)配套用房的一個(gè)二層地下室基坑支護(hù)進(jìn)行了的設(shè)計(jì)及應(yīng)用研究。本工程基坑深度11.55m,軟土深厚,一側(cè)靠河,一側(cè)鄰路,一側(cè)緊鄰已建廠房。針對工程特點(diǎn)采用排樁加支護(hù)的圍護(hù)措施,本研究結(jié)合信息化技術(shù),對基坑工程圍護(hù)措施的設(shè)計(jì)和施工過程進(jìn)行了研究,實(shí)踐表明,采用適合的基坑圍護(hù)措施,確保了基坑周邊環(huán)境的安全。通過對排樁加支護(hù)的基坑圍護(hù)措施設(shè)計(jì)的應(yīng)用及分析,為類似工程實(shí)踐提供有意義的參考。
Abstract: This paper studies the design and application of a two-story basement foundation pit support for a standard factory building and research and development supporting building in Hangzhou. The depth of the foundation pit of the project is 11.55m with deep soft soil,one side on the river, one side adjacent to road, and one side adjacent to the built factory. According to the engineering features, the row pile and support measures are adopted. This study combines the information technology to study the design and construction process of the foundation pit engineering enclosure measures. The practice shows that the appropriate foundation pit protection measures are adopted to ensure the safety of the environment around the pit. Through the application and analysis of the design of foundation pit protection measures for row piles and supports, it provides a meaningful reference for similar engineering practice.
關(guān)鍵詞:基坑;周邊環(huán)境;排樁支護(hù);監(jiān)測
Key words: foundation pit;surrounding environment;row pile support;monitoring
中圖分類號:TV551.4? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ?文獻(xiàn)標(biāo)識碼:A? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? ? 文章編號:1006-4311(2019)34-0115-03
0? 引言
近年來,隨著城市建設(shè)的迅速發(fā)展,地下空間的開發(fā)越來越重要,基坑工程形式也越發(fā)復(fù)雜。排樁作為一種圍護(hù)形式,有其獨(dú)特的優(yōu)勢。
本文以杭州市某基坑工程為實(shí)例,介紹了排樁加支護(hù)的基坑圍護(hù)形式設(shè)計(jì),并對其施工過程及降水措施進(jìn)行了分析總結(jié),對類似工程具有一定的參考價(jià)值。
1? 工程概況及地質(zhì)條件
本工程位于杭州市濱江區(qū),西側(cè)為東冠路,北側(cè)為湯家河,南側(cè)為場區(qū)道路,東側(cè)為場區(qū)空地。工程樁采用鉆孔灌注樁。
基坑西側(cè)的圍護(hù)樁中心線距用地紅線最近約50m以上?;游鞅眰?cè)的圍護(hù)樁中心線距用地紅線最近約2.8m?;?xùn)|側(cè)為場區(qū)空地及已建廠房,圍護(hù)樁中心線距已建廠房最近約25m?;颖眰?cè)的圍護(hù)樁中心線距用地紅線最近約1.7m?;幽蟼?cè)為場區(qū)道路。圍護(hù)樁中心線距道路邊線最近約1.3m。
本工程設(shè)二層地下室,主要底板面標(biāo)高為-10.80,主要計(jì)算承臺底標(biāo)高:-11.90,主要計(jì)算開挖深度為11.55m?;涌偲矫嬉妶D1。
根據(jù)巖土工程詳細(xì)勘察報(bào)告,各土層物理力學(xué)指標(biāo)詳見表1,基坑深度影響范圍場地土層分布(表1)如下:
1-1雜填土:雜色、松散,主要由碎石、塊石、粘性土組成,偶夾建筑垃圾,頂部0.15cm混凝土地坪。層厚0.80~2.50m,層頂埋深0.00m,層底標(biāo)高3.59~5.70m。
1-2雜填土:灰色、松散,濕,主要由粘性土、粉土、粉砂及生活垃圾、建筑垃圾組成,含有少量碎石機(jī)植物根系、有機(jī)質(zhì)。層厚0.45~0.70m,層頂埋深0.00m,層底標(biāo)高4.95~6.05m。
2-1粘質(zhì)粉土:灰黃色漸變成灰色,稍密,濕。局部含有大量粘性土,局部偶夾粉砂薄層,低韌性,搖振反應(yīng)中等。層厚1.40~2.90m,層頂埋深0.40~2.50m,層底標(biāo)高1.49~4.55m。
2-2砂質(zhì)粉土:灰色,中密~密實(shí),濕,含有粉砂、少量粘性土,局部粉砂較多呈粉砂狀,偶夾粘性土團(tuán)塊,干強(qiáng)度低,低韌性,搖振反應(yīng)迅速。層厚5.55~8.10m,層頂埋深2.00~4.60m,層底標(biāo)高-4.78~-2.65m。
2-3砂質(zhì)粉土:灰色,中密,濕,含有粉砂、少量粘性土,偶夾粘性土團(tuán)塊,干強(qiáng)度低,低韌性,搖振反應(yīng)迅速。層厚0.80~2.10m,層頂埋深9.20~10.20m,層底標(biāo)高-6.71~-3.91m。
3淤泥質(zhì)粉質(zhì)粘土:灰色,流塑,飽和,鱗片狀,含有粉細(xì)砂薄層,少量貝殼。干強(qiáng)度高,韌性硬,無搖震反應(yīng)。層厚2.20~5.50m,層頂埋深9.50~12.30m,層底標(biāo)高-9.44~-7.29m。
4-1砂質(zhì)粉土夾淤泥質(zhì)粉質(zhì)粘土,灰色,稍密~中密,濕~很濕,層理明顯,夾粘性土薄層,粘性土單層厚0.2~1.0cm,軟塑狀,夾貝殼碎片,干強(qiáng)度低,低韌性,搖振反應(yīng)慢。層厚3.60~7.30m,層頂埋深13.70~15.70m,層底標(biāo)高-16.53~-12.46m。
4-2粉質(zhì)粘土與砂質(zhì)粉土互層,灰色,稍密~中密,濕~很濕,層理明顯,互層粉質(zhì)粘土,粉質(zhì)粘土單層厚0.2~2.5cm,軟塑狀,局部夾淤泥質(zhì)粉質(zhì)粘土,流塑狀,夾貝殼碎片,干強(qiáng)度低,低韌性,搖振反應(yīng)慢。層厚3.60~7.30m,層頂埋深13.70~15.70m,層底標(biāo)高-16.53~-12.46m。
5-1粉質(zhì)粘土:灰褐色夾灰色,軟塑,飽和,細(xì)鱗片狀,局部夾有粉細(xì)砂團(tuán)塊,少量貝殼碎片、姜結(jié)石。干強(qiáng)度高,韌性中等,無搖震反應(yīng)。層厚1.50~5.10m,層頂埋深28.00~32.40m,層底標(biāo)高-28.97~-24.88m。
場地地下水淺部為孔隙潛水,分布連續(xù)。深部承壓水主要賦存于6層圓礫中,強(qiáng)含水層,水量豐富。地下水水位受季節(jié)影響明顯,水位動態(tài)變化較大,豐水期水位接近地表,枯水期水位埋深約2.5m左右??辈炱陂g地下水實(shí)測水位埋深為0.50~0.80m。
2? 基坑圍護(hù)方案
本項(xiàng)目基坑工程主要有以下特點(diǎn):①基坑開挖深度范圍土層主要為粉土,坑底以下大部分為淤泥質(zhì)粉質(zhì)粘土,粉性土土性較好,透水性強(qiáng),淤泥質(zhì)土土性較差,對基坑穩(wěn)定性不利;②基坑主樓主要開挖深度為11.55m,開挖深度較深;③基坑周邊環(huán)境條件除西北側(cè)和北側(cè)外,其余相對較好。
在確?;影踩那闆r下,充分利用場地優(yōu)勢,基坑上部選擇放坡開挖節(jié)約造價(jià),下部采用鉆孔灌注樁加一道鋼筋砼內(nèi)支撐。
場地內(nèi)土層主要為砂質(zhì)粉土、粉砂,滲透性好,需考慮止水和降水。本基坑采用坑外一排三軸水泥攪拌樁止水局部結(jié)合場地條件采用自滲管井降水,坑內(nèi)自滲管井降水。
根據(jù)以上所述,并通過大量的分析計(jì)算,最后確定采用排樁加一道鋼筋混凝土支撐,坑外一排三軸水泥攪拌樁止水,坑內(nèi)外采用自滲管井降水的基坑圍護(hù)方案。見圖2。
3? 基坑工程施工及降水措施
本工程基坑圍護(hù)施工說明:①場地修整。本場地地坪設(shè)計(jì)標(biāo)高為-0.35,若高出部分應(yīng)進(jìn)行卸土平整;②支撐系統(tǒng)達(dá)80%設(shè)計(jì)強(qiáng)度后,主樓基坑內(nèi)分層、分塊、并盡量對稱挖土。支撐上若要通行機(jī)械,必須先填土高出支撐面30cm后,再鋪設(shè)路基箱板,方可通行。挖土過程中要注意保護(hù)水平支撐、豎向立柱,豎向立柱附近開挖土方的高低差不得大于1.5m;③設(shè)置排水溝、各監(jiān)測點(diǎn)。
基坑外四周設(shè)400×400磚砌排水溝,以排(截)除地表水及基坑內(nèi)抽取的水。每隔30m,設(shè)一個(gè)沉淀池,排水溝的水經(jīng)沉淀池沉淀后排向下水管道,嚴(yán)禁直接排到地下,防止回灌基坑?;觾?nèi)自滲管井可以靈活地布置在承臺之間,在本地區(qū)基坑降水中使用比較多,效果也比較好??觾?nèi)水位要求位于坑底以下0.5~1m;坑外控制性降水,水位標(biāo)高位于自然地坪以下3.5m。
4? 基坑監(jiān)測
根據(jù)本基坑監(jiān)測報(bào)告顯示,基坑圍護(hù)東側(cè)的深層土體水平位移情況見圖3,圖上顯示位移控制情況比較好。但基坑北側(cè)在土方開挖至基坑底部附近時(shí)產(chǎn)生水平位移較大,由于此位置靠近湯家河,施工現(xiàn)場技術(shù)人員及時(shí)采取了斜撐加固的支護(hù)措施。分析原因靠近湯家河附近綠化施工土質(zhì)回填較松散,造成錨索的錨固力減弱。但是整個(gè)基坑的止水效果較好,說明排樁支護(hù)方法對該地區(qū)土層有適用性。
5? 結(jié)論
①在軟土地區(qū),地下室基坑采用排樁的圍護(hù)方式,可滿足周邊環(huán)境對土體位移的要求。
②根據(jù)施工項(xiàng)目周邊環(huán)境的不同,基坑圍護(hù)方案設(shè)計(jì)要有針對性,應(yīng)采用針對性設(shè)計(jì),確保基坑方案既安全又經(jīng)濟(jì)。
③排樁圍護(hù)可根據(jù)基坑深度、周邊環(huán)境及土質(zhì)情況的不同,坑內(nèi)設(shè)置鋼筋混凝土支撐,坑外一排三軸水泥攪拌樁止水的方式。
④基坑的降水很重要,也是基坑施工成功與否的關(guān)鍵,因此應(yīng)高度重視,確保降水質(zhì)量。
參考文獻(xiàn):
[1]劉國彬,王衛(wèi)東,等.基坑工程手冊(第二版)[J].中國建筑工業(yè)出出版社,2009.
[2]宋青君,王衛(wèi)東,翁其平.“二墻合一”深基坑工程設(shè)計(jì)中的若干技術(shù)問題與對策[J].巖土工程學(xué)報(bào),2006,28:1590-1595.
[3]鄒洋.建筑工程中的深基坑支護(hù)施工技術(shù)分析[J].江西建材,2015,6(14):99.